Wide expertise on project delivery around the world

Project search

Turku Central Wastewater Treatment Plant

- Technical studies for various process alternatives
- Process design
- Engineering design
- Engineering geological survey and geological design
- Contract documents and construction supervision of the wastewater treatment area
FCG International Ltd (former FCG Finnish Consulting Group Ltd, Plancenter Ltd) has provided the consulting services for the Turku Central Wastewater Treatment Plant between September 2003 and December 2012, Defects Notification Period (DNP) for main project being 1.1.2009 – 31.12.2010 and Defects Notification Period (DNP) being for process expansion being 1.1.2011 – 30.12.2012.

Project details

Name of client Turun Seudun Puhdistamo Oy
Location Finland
Start date 09/2003
Completion date 12/2012
Origin of funding Turun Seudun Puhdistamo Oy
Name of partners Rockplan Ltd, Pöysälä & Sandberg Ltd, Suomen Malmi Ltd